The second storey construction work will begin at Hermann’s House

The construction works of the six commercial premises and storage rooms on the first floor facing Paldiski Road are about to be completed. On the same ground behind the house, the first floor will comprise of eight parking places.

The structures of the intermediate ceiling of the first floor will be reinforced and poured in July. The hollow panel structures will be installed in two stages in the first half of July. This will create a base for the structures of the second floor. The wall elements of the second floor will be mounted starting from the second half of July.

Concrete wall and ceiling constructions will provide sound and heat isolation and extend the usage of the building.

The basement cement floors will be poured in the middle of July. By now all the piping works are done and the crushed stone filling is laid under the floor.

There are also storage spaces on the underground enclosed parking level and residents can access all floors by the elevator. This makes it easy to reach your destination even with a baby carriage, shopping bags or suitcases. 

www.hermanni.ee

Back

Take a look at our other projects

THANK YOU FOR SUBSCRIBING TO OUR NEWSLETTER.

To be able to send you information that is most relevant to you, we ask that you specify what kind of real estate you are looking for.

Aim for buying

Number of rooms

(please mark all the relevant options)

Balcony

Location

(please mark all the relevant options)

MORE INFO

Did not find a suitable one among the apartments on offer?

  • We will contact you when a new project is coming up.
  • Be among the first to see, and you will have more options to choose from.